Back to news
Impact· 3 June 2026

UNICEF certifies completion of 5 multi-use water systems in Cabo Delgado

Completed in May 2026, the 5 solar-powered systems in Palma and Mocímboa da Praia received a completion certificate from UNICEF.

In May 2026, SC Nasser completed 5 solar-powered multi-use water supply systems in Palma and Mocímboa da Praia districts, including Olumbe, under contract 43432753 (Lot 1) with UNICEF Mozambique.

On 3 June 2026, UNICEF issued a certificate of satisfactory completion. The five systems total 17.8 kW of installed solar PV.